Lake County water battery drilling began as PG&E cut power to 3,601 customers David Brown

A drilling rig began taking core samples for a proposed hillside water battery in Hidden Valley Lake on Oct. 15, the same day a PG&E public safety power shutoff left 3,601 Lake County customers without electricity during a red flag warning. The project is designed to store energy and keep a large water reserve available to firefighters.

Called FLASHES, the project is being developed by Trane Energy Services, with study funding from PG&E’s Microgrid Incentive Program. The timing puts the proposal’s two aims in sharp relief: storing power for use during outages and providing emergency water in a county that has experienced repeated fires. The project is still being studied; the drilling is for core samples, not evidence that construction has begun.

How the water battery would work

Unlike large pumped-hydro projects that rely on dams, FLASHES is designed around tanks and a hillside. A solar field covering more than 100 acres would power pumps that move water from a lower tank to roofed tanks uphill. When electricity is needed, including during an outage, water would flow back down through a turbine to generate power.

The covered tanks are intended to limit evaporation. Developers say the water would come from a dedicated well that could extend more than 1,000 feet underground. Trane’s Michael Day told Lake County supervisors that the project must show it can draw water from a source separate from the local supply. Whether the geology will support that well remains a key question.

Why the upper tank is reserved for firefighters

The upper tank is designed to hold 5 million gallons that would be kept out of the energy system and reserved for firefighting. Day described it as a “never-touch-it emergency fire reserve.” The plan is for that water to be available to firefighters without first running through the turbine.

The project’s energy storage and fire protection are meant to serve different purposes: the battery would store solar power and could sell electricity to California’s grid during peak hours, while the reserve would supply emergency water. A construction schedule has not been announced.