Coastal Commission to weigh OCTA plan to protect San Clemente rail line

The proposal combines rock, a seawall and sand replenishment along a vulnerable stretch of coast, but environmental groups warn that hard protection could worsen beach loss.

Coastal Commission to weigh OCTA plan to protect San Clemente rail line VATO 🫶

The California Coastal Commission is scheduled to consider a plan Thursday, Nov. 5, to protect the rail line along south San Clemente’s eroding coastline with rocks, a seawall and a major sand replenishment project. The Orange County Transportation Authority is seeking permission to retain 48,463 tons of existing riprap, add 2,100 tons of new rock and build a 1,223-foot seawall beside the tracks. The plan also calls for 220 tiebacks to secure the bluff.

The proposal concerns a stretch of the LOSSAN rail corridor, which carries passenger and freight trains between San Diego and San Luis Obispo. Service between San Diego and Orange County has been halted multiple times in recent years because of damage along this part of the line. But the protective structures could take up beach space and worsen erosion, critics say, putting coastal access and shoreline resources at issue as well as rail reliability.

The application includes 690,000 cubic yards of sand, split between sites north of the San Clemente Pier and at the city’s southern end. The larger southern placement would be the biggest sand replenishment project in the city’s history, according to the Orange County Register.

What commission staff recommends

Commission staff recommends approving the project for 10 years, rather than the 30 years OCTA is seeking. Staff proposes conditions including public access improvements, monitoring the performance of the shoreline protection and sand placement, and a mitigation program. The staff report says the approach seeks to balance railroad protection with public access and other coastal resources.

Staff also recommends a long-term railroad adaptation study, due by November 2030, to address the effects of existing and proposed protective structures. The mitigation plan would require at least 690,000 cubic yards of sand and removal of unnecessary rock to open beach space. Sand could come from offshore borrow sites or from a stockpile at Prado Dam, delivered by truck.

Why opponents object

Orange County Coastkeeper is urging commissioners to deny or change the application. The group argues there is no evidence the hard armoring will protect the rail line and says the application does not adequately address damage to the shoreline. Commission staff also noted that OCTA’s proposed maintenance program could allow riprap to be placed along San Clemente’s coastline when needed, but applicants did not specify a maximum volume.

Coastkeeper’s letter says the staff report does not estimate how long the proposed armoring would protect the railroad, if at all. The commission’s decision on the request, including OCTA’s proposed 30-year term, had not yet been announced as of Wednesday.

This report draws on information from Orange County Register.

Editorial checks passed Facts, figures and quotes checked against 1 source